Smart Energy Communities Tea Gardens

Welcome to the Tea Gardens community engagement portal for the Smart Energy Communities trial and thank you for taking part.

Your community has been chosen as part of the trial to explore the unique nature of a gated community for options to better manage power reliability in a private network.

The Smart Energy Communities trial is about testing a future mode of operation of our network as the energy transition continues to pick up pace.

The trial is designed to answer three main questions:

  • How to maximise the export from rooftop solar and communities into the network
  • How to store that energy in our network, and
  • How to return as much of the value of stored energy in Essential Energy assets to the community who generated it.


The trial is being rolled out in stages. We will be updating this portal with the current stage information as we progress through the trial. We encourage you to get involved in the discussion by asking questions, taking part in short polls, and providing honest feedback through surveys.

Welcome to the Tea Gardens community engagement portal for the Smart Energy Communities trial and thank you for taking part.

Your community has been chosen as part of the trial to explore the unique nature of a gated community for options to better manage power reliability in a private network.

The Smart Energy Communities trial is about testing a future mode of operation of our network as the energy transition continues to pick up pace.

The trial is designed to answer three main questions:

  • How to maximise the export from rooftop solar and communities into the network
  • How to store that energy in our network, and
  • How to return as much of the value of stored energy in Essential Energy assets to the community who generated it.


The trial is being rolled out in stages. We will be updating this portal with the current stage information as we progress through the trial. We encourage you to get involved in the discussion by asking questions, taking part in short polls, and providing honest feedback through surveys.

General Questions

Ask your question about the Smart Energy Communities trial here and we will reply to you as soon as we can. If you would prefer to be answered privately just let us know in your question and we will respond so only you see the answer. 

Please note, your question will only be visible on the questions areas after we have responded (assuming you do not request a private answer).

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Please provide a copy of the Electricity Act - requested by a Palm Lakes resident.

    6 months ago

     

    Thank you for your question. 
    The Environmental Planning and Assessment Act 1979 (EP&A Act) contains a number of approval pathways (and exemptions) for certain types of developments and activities.

    Development that is permissible with consent requires that a Development Application (DA) is submitted to council for consent. Another category of development that exists under the EP&A Act, is development permissible without consent. Developments involving electricity networks are considered as 'development permissible without consent' as per State Environmental Planning Policy (Transport and Infrastructure) 2021 (T&I SEPP).

    The installation of batteries meets the definition of an 'electricity transmission or distribution network' as per the T&I SEPP. As Essential Energy is considered a public authority for the purposes of the EP&A Act, Essential Energy has an obligation to consider the potential impacts under Part 5, Division 5.1 of the act.
  • Hello, Can you advise me if any consideration has been given to the impact of potential blight upon property values adjacent or near any future batteries. Thank you.

    ID asked 6 months ago

    Thank you for your question. Whilst we are not aware of any evidence suggesting property values are negatively impacted due proximity to batteries (particularly where that property was located close to existing electricity infrastructure already) it is difficult to assess the impacts of batteries until we understand the available options for PLR. We would also suggest it is possible that property prices will be positively affected by the batteries as they assist in achieving Net Zero as well as providing benefits to the community. 

    Once we have a list of the suitable battery options, we will let you know and ask each resident to either opt-in to the battery closest to them or opt-out. Based on the level of agreement we will decide which battery locations are feasible and worth our investment as part of the SEC trial.

    Essential Energy strongly encourages residents to assess how SEC benefits will impact them (both positively or negatively, including any perceived or unintended negative impacts to the community as a whole). We are also discussing each stage of the SEC trial with PLR Management, so they can consider if our trial impacts their ability to meet their obligations to residents. We are very appreciative of PLR Management’s support to date.

  • When you were at Tea Gardens the other day, you were saying, words to the effect of, that you don't know what would be the best way to shield a battery in relation to noise or camouflaging - that there were numerous details to take into consideration prior to deciding on the best course of action. How do you actually work out how to arrive at the best course of action - do you instal the battery and then, somehow, carry out tests to see what will suit the purpose? How I heard it, the only noise that may occur would be from then fan going on intermittently. Please advise, and many thanks.

    Jennifer Newman asked 7 months ago

    Hi Jan,

    thank you for your question it is a popular topic at the moment. Essential Energy intends to install the batteries with factory installed noise abetment, we anticipate this will alleviate noise concerns. In the event that there is still nuisance noise then Essential Energy would be looking to perform location-based studies as noise can be affected by existing background noise, local structures, and geographical features which cannot be readily anticipated before installation. We would then take remedial steps including, altering the way it operates, installing more noise mitigation solutions or shutting the system down for periods of time. It is correct that the noise is intermittent based on what the battery is being asked to do at a certain time.

    thank you again for your question!

    Smart Energy Communities Trial team

  • A question from a 16 October chat with residents living around the western transformer...Will there be charges or contracts involved with the community battery capability?

    GregT asked 7 months ago

    Customer offerings are yet to be determined and are predicated on a regulatory waiver.

  • A question from a 16 October chat with residents living around the western transformer...Will there be any noise involved once the battery is installed?

    GregT asked 7 months ago

     All the proposed battery have some level of operating noise. This noise level is dependent on the demand on the battery and ambient temperatures . Essential Energy is working with suppliers to investigate noise abatement solutions to further minimise operating noise.

  • A question from a 16 October chat with residents living around the western transformer...Are residents likely to be better off if we take advantage of this community battery proposal?

    GregT asked 7 months ago

    Yes, we fully expect the use of battery storage to be financially benefical. As a safeguard, we will be applying a no disadvantage principle.

  • A question from a 16 October chat with residents living around the western transformer...Are Palm Lake Resort (PLR) planning to participate in the community battery proposal to help reduce cost of power to our common facilities?

    GregT asked 7 months ago

    PLR will be offered the same opportunities as the residents of PLR, including residents with and without solar systems.

  • A question from a 16 October chat with residents living around the western transformer...If the community battery proposal is acceptable, will everyone have to take part or will residents have a choice?

    GregT asked 7 months ago

    All stages of SEC are opt in, it is entirely your choice to participate.

  • Do Palm Lake Resort, as owners of the property, have to give permission for installation of the community batteries or is the installation a negotiation between EE & PLR?

    Jennifer Newman asked 8 months ago

    Hello, 

    There are a number of factors that influence requirements for formal permission, particularly whether the battery will be larger than the existing easements around the substations. 

    Essential Energy intends to discuss the battery placement and logistics/legal considerations with both Tea Gardens PLR manager (Kym) and Palm Lakes Resort management in Qld once the battery tender has been finalised, as this will be when we can openly discuss the available /most suitable options for Tea Gardens.

  • The survey you released last week asked a question about sizing of the battery (in Q8). Roughly how many homes would the SMALL and VERY SMALL enclosures support ? (Lets assume each home was allocated a 10kWh space on the battery / day)? I am interested in understanding whether the smaller enclosures are viable for our village.

    GregT asked 8 months ago

    Thank you for your question. There are a lot of variables for the battery sizing and capacity which are taken into account to determine the physical size. The survey question is intended to gauge how acceptable the different sized batteries would be to you. We will provide more detailed information in future, once we have finalised the battery tender evaluation. As the technical members of our team are on holidays this week I cannot give you an estimate, but I will post an additional response to this question early next week (if they are able to provide this information).