Happy new year!
We've made it to 2025, and things are starting to get really exciting as we close in on completion of the project.
During December and through to February the cables for the underground component of the line are being installed and we're ready to install aerial markers on the overhead component of the line. The markers (red and white balls to the naked eye) are to help identify powerlines to aircraft and are being installed following consultation with Canberra airport- safety is always our number one priority!
Next steps from here will be to energise the powerlines, with our full demobilisation from site on track to be completed by April this year.
Some progress pictures of the Zone Substation and an example of what the aerial markers will look like are below.



Share How are things progressing? on Facebook
Share How are things progressing? on Linkedin
Email How are things progressing? link
Share Vegetation Clearing Completed on Facebook
Share Vegetation Clearing Completed on Linkedin
Email Vegetation Clearing Completed link
Contractors for Essential Energy have recently completed vegetation clearing along the route of the new powerline installation. The works have certainly tidied things up quite a bit, particularly along the disused rail corridor.
Cheers,
Josh
Share Construction of Essential Energy Zone Substation on Facebook
Share Construction of Essential Energy Zone Substation on Linkedin
Email Construction of Essential Energy Zone Substation link
Construction of the new Essential Energy Zone Substation is well underway with much of the civil works completed.
With foundations due to be completed by Christmas 2023, we're looking forward to seeing construction of the buildings commence in 2024.
Cheers,
Josh


Share Review of Environmental Factors (REF) update on Facebook
Share Review of Environmental Factors (REF) update on Linkedin
Email Review of Environmental Factors (REF) update link
Below are links to the South Jerrabomberra High Voltage Supply - substation and powerline construction REF's which are published on the NSW Planning portal.
Share Department of Regional NSW - South Jerrabomberra Regional Job Precinct on Facebook
Share Department of Regional NSW - South Jerrabomberra Regional Job Precinct on Linkedin
Email Department of Regional NSW - South Jerrabomberra Regional Job Precinct link
Community update
|
The NSW Government is pleased to provide an update on the master planning for the South Jerrabomberra Regional Job Precinct.
Read the full update here.
|
 |
Share Public consultation on draft Environmental Impact Statement (EIS) and Development Application (DA) on Facebook
Share Public consultation on draft Environmental Impact Statement (EIS) and Development Application (DA) on Linkedin
Email Public consultation on draft Environmental Impact Statement (EIS) and Development Application (DA) link
A requirement of ACT Government is to submit a draft Environmental Impact Statement (EIS) and concurrent Development Application (DA).
An EIS details the anticipated environmental impacts of a development on the environment as well as proposing avoidance, mitigation and offset measures.
The public consultation period commenced 28 March 2023 and closed on 18 May 2023.