On 18 June 2020, Construction New 20-03 Installation of Spare Conduits in New Installations was released.

After receiving feedback, Essential Energy has amended underground drawings CEOM7201.02 and CEOM7201.11 to clarify that installation of 25-50mm2 supply cables is permitted in 50mm HD orange conduit. Any spare conduit that is required to be run with the supply cable must be a minimum of 125mm orange conduit.

Please refer to the drawings for conduit part numbers for the installation type.

What do you need to do?

  1. Review the Construction New 20-03 Installation of Spare Conduits in New Installations, available on the Document Library.
  2. Communicate this information to relevant members of your organisation.