You cannot leave comment in this blogpost unless you are a part of the project panel.

Project Compliance - Surveyor’s Advice Update

What is Happening?

To comply with section 2.12 of CEOP2015, all contestable overhead and underground projects that include easements and/or allocations such as road reserves and nature strips require a surveyor’s letter stating that the network assets gifted to Essential Energy are in the locations indicated on the certified plan/s.

The surveyor’s letter must be submitted on your company letterhead with the project completion document. To assist, an example letter can be found on the Document Library.

What do you need to do?

  1. Review the above and ensure these requirements are met.
  2. Communicate this information to relevant members of your organisation, customers and proponents.

Further Information

If you need further information, please email aspinfo@essentialenergy.com.au.