NGK Stanger gas switch supply update

What is Happening?

While availability of NGK Stanger Pty Ltd gas switches has improved in the last few months, lead time for purchasing directly from NGK Stanger is currently a minimum of 8 weeks. Please factor this into your project plans.

If you need switches sooner for any critical jobs, you can purchase them through Essential Energy’s external sales team by emailing external.sales@essentialenergy.com.au.

What do you need to do?

  1. Communicate this information to relevant members of your organisation.
  2. View this communication via Essential Engagement.

Further Information

If you require further details, please contact NGK Stanger Pty Ltd customer service team via email at sales@ngkstanger.com.au or Essential Energy’s external sales team via email at external.sales@essentialenergy.com.au.