Clarification on Live Connection Request Lead Times
What's happening?
Essential Energy wishes to clarify the requirements outlined in CEOP2015 - Division Procedure: Contestable Works Guidelines (Terms and Conditions for Contestable Works) 2.8.2.8 Request for Connection.
The current issue 14 states that a minimum of 5 days’ notice is required for Live Connections, this applies only to ‘Live Work Requests.’ For Connection Requests where Essential Energy performs the live connection, connection requests must be lodged a minimum of 28 days prior to the connection date.
What do you need to do?
- View CEOP2015 - Division Procedure: Contestable Works Guidelines (Terms and Conditions for Contestable Works) via the Document Library.
- Communicate this information to relevant members of your organisation.
Further Information
If you need further information, please email aspinfo@essentialenergy.com.au.