Clarification of variations to CEOM7206.04 Standard Streetlight Footing Designs

Background

Following recent questions, we have outlined below what Essential Energy requires to accept requests for variations to CEOM7206.04 streetlight footing designs.

Certification of variations

Prior to submitting a streetlight footing design to Essential Energy that varies from CEOM7206.04 (e.g. with alternative cage designs, depth, etc), Level 3 ASPs must ensure the design has been certified by a suitably qualified civil engineer, and provide a copy of this certification to Essential Energy as an accompanying letter. The alternative design can then be certified with the original submission.

At the time of construction, if a Level 1 ASP requests a variation to a plan certified by Essential Energy, variations will need to be resubmitted for re-certification by the Level 3 ASP. Any variations will incur the standard fees charged by Essential Energy.

Please also note that variations identified within ‘As-Built’ drawings or designs may not be accepted by Essential Energy.

Future improvements

If you have any feedback about our existing Standard/s, or suggestions for future improvement, such as potential cost reductions or efficiency gains that could be achieved without impacting quality or safety, please send them to aspinfo@essentialenergy.com.au for consideration on future revisions.

What do you need to do?

Communicate this information to relevant members of your organisation.

Further Information

If you need further information, please email aspinfo@essentialenergy.com.au.