Changes to Planned Outage Reschedule Lead Times
What is Happening?
From 1 November 2021, a twenty-two (22) day lead time is required to reschedule an outage.
PLEASE NOTE: The process for new outage requests remains the same. Level 1 ASPs must submit an original completed CEOF6013 Notice of Required Outage/Connection form via email to contestableworks@essentialenergy.com.au as soon as practicable. Provided submission is a minimum of twenty-eight (28) days prior to the requested outage date, outage requests may be submitted at any time from commencement of construction. A longer lead time for an outage request will substantially increase the likelihood of securing the preferred commissioning date.
What do you need to do?
Communicate this information to relevant members of your organisation.
Further Information
If you need further information, please email aspinfo@essentialenergy.com.au.