Progress Update 23 May 2025
CLOSED: This discussion has concluded.

Boring of foundations for the new poles is underway with holes mostly completed between Birch Avenue and the Mitchell Highway. Concrete has been poured which will take a few weeks to cure and then we can return to erect the new power poles in this section.
Next week (26 May), we will commence boring of foundations from Hindmarsh Esplanade, heading south towards our Zone Substation near the greyhound racing club. We don't anticipate any impacts to roads or traffic but there will be noise from the drilling rig as it bores holes during normal construction hours.