Progress Update 17 July 2025

CLOSED: This discussion has concluded.

As we continue to make our way south through Keswick drilling holes, we've been able to commence standing new poles where concrete foundations have cured around Birch Avenue and Hennessy Drive.

See some pictures below of the new poles.